Placement of the steel continues





A steel beam had to be added to the old North Porch.


The new Gift Shop is being framed in.






Look out over the new addition to the Strader Hall of Champions and the Founders Room.

The Elevator Shaft

Monday, January 5, 2009

Inside Construction Photos


The forms for the foundation are all set and pouring will begin tomorrow at 10am.


The former North Porch has been gutted. This portion of the porch will be the new Gift Shop.


This view is the new doorway into the Foresman Forum.


This view is the front view of the new expanded bathrooms. It is almost double the size of the old bathrooms.


View of half the main dining room.